How do I get a custom calendar loaded in Project Server

J

Joe

When I tried to Import the resources into project server, I was not able to
add my custom calendar. Is there any way to add the custom calendar onto the
project server?
 
D

Dale Howard [MVP]

Joe --

Open the Enterprise Global file, open the project containing the calendar,
and then use the Organizer to copy the calendar to the Enterprise Global.
Hope this helps.
 