Hi;
I marked the task assigned to a resource for today & tomorrow as 100%
done - but it still doesn't start the next task until Wednesday. How
do I get it to understand that completed tasks require no time?
thanks - dave
david@[email protected]
Windward Reports -- http://www.WindwardReports.com
me -- http://dave.thielen.com
Cubicle Wars - http://www.windwardreports.com/film.htm
I marked the task assigned to a resource for today & tomorrow as 100%
done - but it still doesn't start the next task until Wednesday. How
do I get it to understand that completed tasks require no time?
thanks - dave
david@[email protected]
Windward Reports -- http://www.WindwardReports.com
me -- http://dave.thielen.com