How do I get it to adjust for completed tasks?

J

Jack Dahlgren MVP

Enter the actual finish date for the task.

If it is done today, then set today as the actual finish.

-Jack Dahlgren
 
D

David Thielen

that did it -- except the task completed was part way down a list of
tasks and it then adjusted everything following to start today - even
though 2 preceeding tasks are not done.

My situation is that I have
Main task
+ sub task 1
+ + task 1
+ + task 2
+ + task 3
+ + task 4
+ + task 5
+ sub task 2

I have just set each to have the previous as a predecessor as I can't
figure out how to tell it to just allocate days where each resource
can only work 8 hours/day.

When I mark task 4 finished yesterday, but tasks 1, 2, & 3 still need
work, it starts task 5 today and sub task 2 tomorrow. Do I need to
re-do the predecessors when a task is completed prior to the ones
before it?

thanks - dave



Enter the actual finish date for the task.

If it is done today, then set today as the actual finish.

-Jack Dahlgren


david@[email protected]
Windward Reports -- http://www.WindwardReports.com
me -- http://dave.thielen.com

Cubicle Wars - http://www.windwardreports.com/film.htm
 
J

Jan De Messemaeker

Hi,

You shouldn't set predecessors that aren't any: as you have discovered, that
creates tons of work during tracking.
You assign the resoreuce(s) to the task then use ResourceLeveling, which
will ensure resoruces aren't laoded more thatn the working hours.
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
D

David Thielen

Thank you - that mostly worked (new question below).

thanks - dave


Hi,

You shouldn't set predecessors that aren't any: as you have discovered, that
creates tons of work during tracking.
You assign the resoreuce(s) to the task then use ResourceLeveling, which
will ensure resoruces aren't laoded more thatn the working hours.
HTH


david@[email protected]
Windward Reports -- http://www.WindwardReports.com
me -- http://dave.thielen.com

Cubicle Wars - http://www.windwardreports.com/film.htm
 