David Thielen
Hi;
Ok, I am now using resource leveling - works great. But...
1) If I have tasks that are not complete, but they were scheduled for
before today, they are no pushed out to show that they will still
require resource time.
2) If I have tasks that are partially or fully done, but their start
time is after today, they still show as requiring all of their time in
the future.
I'm scheduling for software so by definition the work comes in in a
different order than projected. How do I handle this?
thanks - dave
david@[email protected]
Windward Reports -- http://www.WindwardReports.com
me -- http://dave.thielen.com
Cubicle Wars - http://www.windwardreports.com/film.htm
Ok, I am now using resource leveling - works great. But...
1) If I have tasks that are not complete, but they were scheduled for
before today, they are no pushed out to show that they will still
require resource time.
2) If I have tasks that are partially or fully done, but their start
time is after today, they still show as requiring all of their time in
the future.
I'm scheduling for software so by definition the work comes in in a
different order than projected. How do I handle this?
thanks - dave