M
Mary Beth
i have a project plan that was started from scratch. I have the normal
Summary tasks followed by subtasks. I have entered all of my subtask
duration but the plan is not 'rolling up' those durations for me and
calculating my summary task durations. is there a setting I need to make to
make this roll-up happen?
Summary tasks followed by subtasks. I have entered all of my subtask
duration but the plan is not 'rolling up' those durations for me and
calculating my summary task durations. is there a setting I need to make to
make this roll-up happen?