I have several projects and small tasks in corporate master project plan that
do not have resources assigned (they are for information only). When I go to
the Resource Usage tab, the items show up under the Unassigned. And it shows
40 hours of remaining availability for this "unassigned" resource. I've tried
to edit "unassigned" to not be available, but MSP 2007 does not allow me to
edit the availability. How do I remove this availability so those hours are
not counted when I run Resource availability reports? It can add up to
hundreds of hours when I run a report for a rolling three-month period.
Thanks for the help!
do not have resources assigned (they are for information only). When I go to
the Resource Usage tab, the items show up under the Unassigned. And it shows
40 hours of remaining availability for this "unassigned" resource. I've tried
to edit "unassigned" to not be available, but MSP 2007 does not allow me to
edit the availability. How do I remove this availability so those hours are
not counted when I run Resource availability reports? It can add up to
hundreds of hours when I run a report for a rolling three-month period.
Thanks for the help!