How do I get the Cumulative Work from a Baseline in Project 2003?

G

Gustavo - Brazil

In the Task Usage section, I'm trying to see the Cumulative Work and the
Baseline Cumulative Work to compare, but the option "Baseline Cumulative
Work" does no exist.
 
J

Jan De Messemaeker

Hi,

Since it doesn't exist, no way to show it, sorry.
If you can export the values to Excel you could make something there
yourself...

Greetings,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 