How do I group tasks together with a Header?

C

Clarissa010101

I can't figure out how to groups tasks together with headers, as the
Uber-project has many smaller projects within it, that then break down into
specific tasks.

Thanks!
 
J

José Miguel Piñeres

Hello,

Have you tried using the "Project" field in the group configuration? You can
group by Project, then use any other criteria you may need.

I hope this helps.
 
J

JulieS

Hello Clarissa,

Insert the "header" task and in the rows underneath insert the
specific tasks -- one on each row. Select the tasks underneath the
header task and click the Indent button to indent the selected tasks
and make the "header" task a summary task. See the help topic
"Outline tasks into subtasks and summary tasks."

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top