I am using Microsoft project 2000. I have a project that runs over a large
timescale and I want to only see part of that timescale in my Tracking Gantt.
The problem lies in that the overall task for the project runs the full
timescale and therefore it creates lots of pages when I use a detail level on
the tracking calendar part. i want to hide part of the date range. Using a
filter doesn't work as this top task always has something under it. I can
also zoom out on the timescale but this then loses the detail that I need to
see.