M
Maryfr
Hi I am setting up a project and in the duration column I want to show the
total number of days required for the project including non working days -
i.e if a task takes 6 days and starts on a Monday, if Sat and Sun are non
working the task is finished on the following Monday but has taken 8 days to
complete (including non working time).... Does anyone know how i can show
this?
Tks
total number of days required for the project including non working days -
i.e if a task takes 6 days and starts on a Monday, if Sat and Sun are non
working the task is finished on the following Monday but has taken 8 days to
complete (including non working time).... Does anyone know how i can show
this?
Tks