How do I insert on going tasks without an end date?

N

NDK

I have an ongoing Task in my Project. How can I insert the Task into my
Project Plan without an end date?
 
J

JulieS

Hello NDK,

Sorry, that is not possible in Project. All tasks have start dates,
finish dates and duration. If you are looking to add a tasks whose
duration changes as the project finish date is adjusted, see FAQ # 19
"Hammock Tasks" at http://project.mvps.org/faqs.htm

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 