How do I join the Tasks and Resources tables in MS Project/Access

D

djames_d

I have exported a MS Project file to MS Access for reporting purposes and am
attempting to join the MSP_RESOURCES table to the MSP_TASKS table. My
initial analysis shows that there is no direct link between the two tables.
I have discovered a RES_CAL_UID and TASK_CAL_UID column that could be a
potential join; however, only the RES_CAL_UID has values, the TASK_CAL_UID is
-1 for all entries.

If anyone has a tip on how I can join these two tables, I'd greatly
appreciate it.

Thank you in advance. I initially posted this in the Access group and was
directed here.
 
J

JackD

There is no need to do a join between them The data is already in the
MSP_ASSIGNMENTS table, You can join that to MSP_TASKS and MSP_RESOURCES
based on the ids.
 