MS Project 2000 - My duration changes from 30 days to 37.5 days when I use a
7-10hr day calendar instead of my standard calendar (8 hrs per day). Is
there any way to get it to show the 30 days on this task without affecting
other task?
7-10hr day calendar instead of my standard calendar (8 hrs per day). Is
there any way to get it to show the 30 days on this task without affecting
other task?