How do I keep tasks together while Leveling Resources even with available time to split them up?

S

SPepper

How can I keep two or more tasks together when Resource Leveling even i
there is slack available to fit other tasks in between. For example:

- I would like to keep these two tasks together to follow immediatel
after one another:

1.0 Install Software Resource A
2.0 Test Software Resource A 1.0 Dependancy

Neither of the tasks are on the critical path.

Any help would be appreciated.

Thanks,
Stev
 
J

Jan De Messemaeker

Hi,

You won't be absolutely sure but if you give the second taske a 999 priority
and level Priority, Standard, things will work out.
Hope this helps,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top