G
Gwyn
Resource levelling in project seems useless.
All assignments have to be specified as a percentage of a resource
Whereas I want to specify a task with an elapsed time and an amount of
effort. And actually I don't care whether the resource does 100% for the
first 5 days and nothing for the rest or whatever.
So my problem starts when I've got a task, Task A, that runs for 4 weeks
that has 2 man weeks of effort required by a resource. Project takes this to
mean that the resource will be working 50% on this task (but that's not
really what I mean)
I now have 2 days (in the middle of the 4 weeks) when I want this resource
to be 100% occupied on something else, Task B. i.e. this task has an elapsed
time of 2 days and effort of 2 days.
So I would expect to be able to ask Project to level this out using a flat
contour and it would allocate the resource to Task A for a bit more than 50%
for all except the 2 days of Task B, where the resource will be 100% working
on Task B.
This makes absolute sense. However, project will not do this. It shows the
resource as being overallocated on those 2 days. If automatic levelling is
chosen then it will stretch Task A by two days.
Is there any way of making it work *correctly* ???
All assignments have to be specified as a percentage of a resource
Whereas I want to specify a task with an elapsed time and an amount of
effort. And actually I don't care whether the resource does 100% for the
first 5 days and nothing for the rest or whatever.
So my problem starts when I've got a task, Task A, that runs for 4 weeks
that has 2 man weeks of effort required by a resource. Project takes this to
mean that the resource will be working 50% on this task (but that's not
really what I mean)
I now have 2 days (in the middle of the 4 weeks) when I want this resource
to be 100% occupied on something else, Task B. i.e. this task has an elapsed
time of 2 days and effort of 2 days.
So I would expect to be able to ask Project to level this out using a flat
contour and it would allocate the resource to Task A for a bit more than 50%
for all except the 2 days of Task B, where the resource will be 100% working
on Task B.
This makes absolute sense. However, project will not do this. It shows the
resource as being overallocated on those 2 days. If automatic levelling is
chosen then it will stretch Task A by two days.
Is there any way of making it work *correctly* ???