I am working on project server and currenty want o know that is there any way
to display the rollup milestones for a project in the project center view on
the gannt chart grid.
 
K

Kevin W Flanagan

Sunil-

Dale is right in that there is no out-of-the box functionality that will
give it to you. You can use ASP pages and stoplights to get a Milestone
Report by using a custom text field "Milestone Explanation" and a flag
"Milestone Report". This allows you to create any task in your schedule as a
Milestone for reporting purposes and it can show visibly the status of each
milestone.