D
Dana Scott
Hello
I am using Project 2007 to help manage Hospital Construction for a
contractor. What I am trying to do is move the start date of a group of
tasks, either earlier or later, based on changing conditions. If one trade
(i.e. plumbing) needs to adjust their schedule, the timing of the group of
tasks needs to stay the same (or relatively so), but the tasks do not all
occur immediately following one another, this allows time for other trades to
perform their work.
So if I have 13 tasks spread over 150 days with several 10-20 day time gaps
and I need to move the start date earlier, I have to adjust each one
individually. I have tried hard and soft constraints, but cannot get that
time gap to remain fixed.
With thousands of tasks and years on the schedule, this can get a little
tedious. I have looked some macros that may help this, but haven't found
anything to fit the bill.
I welcome any advice, and thank you in advance for your help
I am using Project 2007 to help manage Hospital Construction for a
contractor. What I am trying to do is move the start date of a group of
tasks, either earlier or later, based on changing conditions. If one trade
(i.e. plumbing) needs to adjust their schedule, the timing of the group of
tasks needs to stay the same (or relatively so), but the tasks do not all
occur immediately following one another, this allows time for other trades to
perform their work.
So if I have 13 tasks spread over 150 days with several 10-20 day time gaps
and I need to move the start date earlier, I have to adjust each one
individually. I have tried hard and soft constraints, but cannot get that
time gap to remain fixed.
With thousands of tasks and years on the schedule, this can get a little
tedious. I have looked some macros that may help this, but haven't found
anything to fit the bill.
I welcome any advice, and thank you in advance for your help