Hi,
There are several ways.
1. If your project contains actuals (probably not the case since it didn't
start yet, but who knows) set all tasks to 0 %complete
2. If your project contains constraints (that inludes whn you have set start
or finish dates manually):
Tools
Customize
Toolbars
Check Analysis
From the Analysis toolbar run Adjust Dates
3. If your project does not contains constraints, the following ois
sufficient:
Project menu
Project Information
Set Project Start
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional