How do I move the entire project forward by one month

R

Redman

I have created the project plan and the start date has been put back by one
month is there an easy way to do this.
 
J

Jan De Messemaeker

Hi,

There are several ways.
1. If your project contains actuals (probably not the case since it didn't
start yet, but who knows) set all tasks to 0 %complete
2. If your project contains constraints (that inludes whn you have set start
or finish dates manually):
Tools
Customize
Toolbars
Check Analysis
From the Analysis toolbar run Adjust Dates
3. If your project does not contains constraints, the following ois
sufficient:
Project menu
Project Information
Set Project Start

HTH


--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top