I'm fairly new to using MS-Project. I have created a simple plan and
baselined it. So I am updating progress to the plan.

How do I plot this information graphically? I have manged to display the
'analyse timescaled data wizard, but when I click on it nothing at all
happens. Please what I'm I doing wrong?

Many thanks
JulieG
 
J

JulieD

Hi JulieG

does the Tracking Gantt view give you what you want?

I have had a problem in the past where the Analyse Timescaled data wizard
doesn't work, Nick Pomponio posted this answer back in 2002 on some ideas
for getting it working:
This has happend to me a few times. Here are some notes that I made the
last time the problem occurred:
To fix the problem with the Analyisis Toolbar being inactive, I did the
following:
1) Registered the following ActiveX controls:
C:\Program Files\Microsoft Office\Office\ADJDATE.DLL
C:\Program Files\Microsoft Office\Office\ANLYZTS.DLL
C:\Program Files\Microsoft Office\Office\PERTANL.DLL

2) In Project, go to menu item Tools | Customize | Toolbars.
3) Choose "Tools" category and "COM Add-Ins..." command.
Drag this as a button to a toolbar.
4) Get out of Customize, and click the COM Add-Ins button.
Select the tools from the list.

Hope this helps,
-Nick Pomponio

Let us know how you get on
Cheers
JulieD
 
J

JulieG

Hi JulieD

Thanks very much that worked a treat

JulieD said:
Hi JulieG

does the Tracking Gantt view give you what you want?

I have had a problem in the past where the Analyse Timescaled data wizard
doesn't work, Nick Pomponio posted this answer back in 2002 on some ideas
for getting it working:











Let us know how you get on
Cheers
JulieD
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top