J
Jonathan Hand
This can be reproduced very simply by creating a new blank project then
creating 2 half day tasks assigned to the same resource. Both tasks get
scheduled to run simultaneously and generate a 200% allocation of the
resource.
If you then add a third task of hald a day with the same resource then the
three tasks are scheduled to run sequentially as you would expect.
So why does it go wrong with just 2 tasks and are there any work arounds?
creating 2 half day tasks assigned to the same resource. Both tasks get
scheduled to run simultaneously and generate a 200% allocation of the
resource.
If you then add a third task of hald a day with the same resource then the
three tasks are scheduled to run sequentially as you would expect.
So why does it go wrong with just 2 tasks and are there any work arounds?