Hi Peter,
Two choices:
1)Drag the split bar separating the Gantt chart (graphic) and the task sheet
(data) all the way to the right of the screen.
2) View just the task sheet (View --> More Views select the task sheet and
click apply.)
Hope this helps. Let us know how you get along.
Julie
Peter,
Either use the Task Sheet view, (it doesn't have the Gantt graphic), or
put your cursor on the vertical dividing line between the tabular data
and the graphic information and drag it to the extreme right of your
screen.
Hi Peter,
Two choices:
1)Drag the split bar separating the Gantt chart (graphic) and the task sheet
(data) all the way to the right of the screen.
2) View just the task sheet (View --> More Views select the task sheet and
click apply.)
Hope this helps. Let us know how you get along.
Julie