how do I retrieve Effedates and Rates

T

TomL

MSP 2003 SP1 Server

We need to know where the effective dates and rates are stored in the
database. We are opening the Enterprise resource pool, double clicking on
the resource name, and putting in effective dates and rates. We have noticed
the changed rates do not seem to propogate to a project until it is opened
and saved again.

We assumed it was MSP_RESOURCE_RATES table but testing shows that is not the
case.

Does anybody know where these rates and dates are stored in the Server DB?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Similar Threads


Top