I have a Task that is three days in duration. 3 sub tasks go to make it up
and they are 2 x .5d and 1 x 2d.
Starting as early as possible and finishing before Dec 14 (the deadline),
how can I schedule the task so that the resource has been assigned 3 days but
can do them in a period of between now and Dec 14??
This is driving me nuts.
Thanks for the help