N
Norm Bowler
I have a well-understood task (reviewing the output of an automated daily
build) that I want to assign to one specific person for one hour per day over
a known range of dates.
I am new to Project, but am working with someone who has a lot of
experience. Neither one of us can make this work as expected. I have
experimented with various combinations of fixed-work tasks and assigning
resources at less than 100%, and have never gotten what I wanted.
Intuitively, it seems like if I define a task as 10 hours long and assign it
start day x and resource y allocated at 13%, the complete date should be 10
working days after the start date and the duration should still show as 10
hours.
Is there a way to do that in Project?
Thanks in advance for your replies,
nb
build) that I want to assign to one specific person for one hour per day over
a known range of dates.
I am new to Project, but am working with someone who has a lot of
experience. Neither one of us can make this work as expected. I have
experimented with various combinations of fixed-work tasks and assigning
resources at less than 100%, and have never gotten what I wanted.
Intuitively, it seems like if I define a task as 10 hours long and assign it
start day x and resource y allocated at 13%, the complete date should be 10
working days after the start date and the duration should still show as 10
hours.
Is there a way to do that in Project?
Thanks in advance for your replies,
nb