Is there a reason you just don't "git 'er done?" In other words, if the
resource was available to give it his full attenion and get it done ASAP
once the task starts, why drag it out over 30 days? The duration of a task
is not the "window of opportunity" between when the task is able to start
and when it is due. Instead it is your estimate of the length of time it
will actually be in-progress between when it finally DOES start and when
work will actually be completed. If the resource will devote his full
attention to the task at hand after it does start, working at it steadily
without doing other things at the same time, the 30 hour task will take a
little less that 4 days to wrap up. If at all possible, making the primary
objective to get the overall project done in the shortest time possible,
you'd want to schedule the task with 4 days duration with a deadline of the
required due date and assign the resource 100%. But, assuming you have a
good reason to drag it out, not wanting or able to tie up the resource for
his full workday, for example, it's the resource assignment that will
stretch a 30 man-hour task out over 30 days. One hour per day is
approximately a 12.5% resource assignment, assuming an 8 hour workday. A 30
day duration task with the resource assigned 12.5% will result in 30
man-hours of work being done, the scenario you're looking for. Enter the
task with 30 Days as the duration, assign your resource at 12.5% and you're
all set with the task ending 6 weeks after it starts (30 Days duration is 30
Working days, 6 weeks at 5 working days per week. If you want it to end 30
calendar days later, that's approximately 20 days duration, not 30, because
the 2 non-working weekend days each week don't count in the duration
numbers.)
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://project.mvps.org/faqs.htm for the FAQs
tbrown7777 said:
How do I schedule a task that's due in 30 days, but only takes 1 hour of
work
each day? Project assumes that all 30 hours are done at once when it
schedules. Is there a way to constrain a task to 1 hour a day?
thanks,
Tim