H
hal
We have programmers who are constantly interrupted during the day and
we figure they get 6 hours on a project during an 8 hour day.
Is there an easy way to put in the tasks for a project using an 8 hour
day, but then somehow adjust to reflect the fact that our resource only
gets 6 hours applied per 8 hour day. I've tried serveral schemes
(project calender, resource calender and resource %) and the ending
date for the project never changes (the project should take longer @ 6
hrs per day).
Or, maybe I approaching this the wrong way? Thanks for any help.
we figure they get 6 hours on a project during an 8 hour day.
Is there an easy way to put in the tasks for a project using an 8 hour
day, but then somehow adjust to reflect the fact that our resource only
gets 6 hours applied per 8 hour day. I've tried serveral schemes
(project calender, resource calender and resource %) and the ending
date for the project never changes (the project should take longer @ 6
hrs per day).
Or, maybe I approaching this the wrong way? Thanks for any help.