P
PJ
Is there a way to schedule a 12 hour session involving 3 resources in a
project plan? I try setting work, but then it extends the duration to
cover all three each puttting in 12 hours - but I need the 12 hours to
be the same 12 hours calendar time since they are supposed to be
sitting in a room to collaborate.
If I can't figure this out, I will just block those 12 hours out on the
resource calendar, but that would mean setting it to a specific date
time rather than Project telling me when it is best to do it....
Any ideas?
project plan? I try setting work, but then it extends the duration to
cover all three each puttting in 12 hours - but I need the 12 hours to
be the same 12 hours calendar time since they are supposed to be
sitting in a room to collaborate.
If I can't figure this out, I will just block those 12 hours out on the
resource calendar, but that would mean setting it to a specific date
time rather than Project telling me when it is best to do it....
Any ideas?