R
RaganStukenborg
As much as we would otherwise prefer, our team spends less than 100% of our
time each week dedicated to projects. In reality, we're about 60% projects
and 40% support. We also tend to work on several smaller projects at the
same time, rather than one large project. Is there a way to set Project to
have the work day reflect the number of hours that are available for project
work, then assign a percent availability to use the number of project hours?
When I tried to set the standard calendar to a 5 hour work day, and allocated
a resource at 50%, they showed as working 4 hours on the project that day,
rather than 2.5.
Thanks
time each week dedicated to projects. In reality, we're about 60% projects
and 40% support. We also tend to work on several smaller projects at the
same time, rather than one large project. Is there a way to set Project to
have the work day reflect the number of hours that are available for project
work, then assign a percent availability to use the number of project hours?
When I tried to set the standard calendar to a 5 hour work day, and allocated
a resource at 50%, they showed as working 4 hours on the project that day,
rather than 2.5.
Thanks