How do I set default calendar view to 5-day work week

G

gubbayp

Hi. I'm trying to setup my calendar view to use the 5-day work week by
default. When I switch to calendar, I have several views appear in my toolbar
at the top of the page. I'm always defaulted to 7-week. I prefer the 5 Work
Week view. When I make that selection it sticks for the current week.
However, as soon as I choose a new week I'm switched back to the 7-week view.

Is there any way to default to the 5 Work Week view?
 
D

DAVE

Hi,
Tools
Options
Preferences tap
Calendar options
Under calendar work week
Uncheck saturday/sunday
Rgrds,
 
G

gubbayp

Hi Dave. Thanks for responding. Unfortunately, this did not fix my issue.
Let me clarify, the "5 Work week" view is different than the "7 Week" view.
The "5 Work week" view shows each day as a vertical column (5 columns in
total - one for each day of the week). When I try to move ahead a week I use
the small monthly calendar. I select the next week by clicking to the left of
a row within the calendar. When the new week shows up in the main calendar
pane it is defaulted back to the "7 Week" view even though I had it in the "5
Work week" view.

Any ideas?

thanks,
Paul
 
M

Milly Staples [MVP - Outlook]

Use the arrow directional buttons to move - when you select the next week
using the date navigator and highlight all seven days, you are requesting a
7 day view. If you want to test this, then hold the control button, select
days (non-contiguous if you prefer) and release the button. Highlighting
the dates in Date Navigator tells Outlook what to display, just as when
selecting the week by pointing to all seven days.

--
Milly Staples [MVP - Outlook]

Post all replies to the group to keep the discussion intact. All
unsolicited mail sent to my personal account will be deleted without
reading.

After furious head scratching, gubbayp asked:

| Hi Dave. Thanks for responding. Unfortunately, this did not fix my
| issue. Let me clarify, the "5 Work week" view is different than the
| "7 Week" view. The "5 Work week" view shows each day as a vertical
| column (5 columns in total - one for each day of the week). When I
| try to move ahead a week I use the small monthly calendar. I select
| the next week by clicking to the left of a row within the calendar.
| When the new week shows up in the main calendar pane it is defaulted
| back to the "7 Week" view even though I had it in the "5 Work week"
| view.
|
| Any ideas?
|
| thanks,
| Paul
|
| "DAVE" wrote:
|
|| Hi,
|| Tools
|| Options
|| Preferences tap
|| Calendar options
|| Under calendar work week
|| Uncheck saturday/sunday
|| Rgrds,
|| --
|| DAVE
||
||
|| "gubbayp" wrote:
||
||| Hi. I'm trying to setup my calendar view to use the 5-day work week
||| by default. When I switch to calendar, I have several views appear
||| in my toolbar at the top of the page. I'm always defaulted to
||| 7-week. I prefer the 5 Work Week view. When I make that selection
||| it sticks for the current week. However, as soon as I choose a new
||| week I'm switched back to the 7-week view.
|||
||| Is there any way to default to the 5 Work Week view?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top