You can set the Gantt chart timeline to units of years if you wish but you
are correct, you can't set task durations to years. The question has to
come up, though - why would you want to? Individual tasks should represent
the work done by a single resource or resource team that produces a single
deliverable. While there are exceptions, if you have individual tasks that
run more than 80 hours or so you're probably not breaking your project down
into sufficient detail. Summary tasks and project phases certainly may last
more than a year but they would contain many hundreds of subtasks that would
get completely lost if you used 'year' as the basic unit of duration.
Timeline with years in the top tier? Certainly. But not for individual
tasks.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://project.mvps.org/faqs.htm for the FAQs
Novbabea said:
In a previous version of Projecf the duration units were able to be set
for
years. Project 2003 does not give me the choice to select years as
duration
units.