How do I set timeline?

G

Gérard Ducouret

Format / Time Scale / Middle tier : Quarters / Bottom Tier : Months

Gérard Ducouret
 
S

Steve House

In the Gantt chart right mouse click on the timeline at the top, choose
timescale from the context menu that pops up and set the major and minor
divisions of your choice

Steve House
MS Project MVP
 
J

John Beamish

Doubleclick on the timeline header. In the popup dialog box, set the middle
tier to quarters and the bottom tier to months. Make certain the Timescale
Options "show" is set to "two tiers (middle, bottom)".

JLB, PMP
 