On the Format menu, select timescale. You can select project days such as
1, 2, 3 from the project start or finish date. This works for all times
(Years, Months, Days, etc.).
For the vertical columns, on the Tools Menu, select Options and then pull
the view tab. Select a date format from the drop down but it will always
marry to a real date.
If you want to re-use this as a "template" then use the Adjust Dates wizard
from teh Analysis Toolbar.
--