how do i set up a shift rota on ms project using 5 shifts

S

Sean

I am using ms 2000 to set up a training programme but I have to match this
programme against a shift rota which is in excel.
 
J

JulieS

Hello Sean,

I'm not sure what a shift "rota" is -- perhaps rotation? You can
create base calendars for the different shift you have through Tools
Change Working Time. If you have shifts which cross midnight,
take a look at the "Night Shift" base calendar for an example.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 