I would like to enter actual work, as well as percent complete, and have
Project calculate the actual duration based on that.
For example, an employee has logged 70 hours total. He estimates that his
work is 80% complete. I would like to avoid having to calculate the duration
manually (hours*100/percent complete).
How do I set this up?
Project calculate the actual duration based on that.
For example, an employee has logged 70 hours total. He estimates that his
work is 80% complete. I would like to avoid having to calculate the duration
manually (hours*100/percent complete).
How do I set this up?