How do I set up subtasks underneath a recurring task in Project?

A

Andy

I am trying to set up a project plan. There is a large task that is
recurring weekly. The large task needs to be broken into many subtasks, but
the whole process is recurring. Is it possible to enter the subtasks once
and have them appear as subtasks under each occurrence of my recurring task?
If so, how?
 
C

Catfish Hunter

If I ubderstand the question: I woluld build the schedule with all the
subtask under the large task (this is called a summary task). Once I got the
logic correct I would copy this group of task and paste them.
 