Hi,
This is a problem because there is an explicit link from the summary task to
its subtaks:
If the start of a summary task is forced by anything else than its subtasks,
no subrtask will start befor the summary
The result will always be that a summary's start and end dates are the
earliest start of any subtask, and the latest finish of any siubtask,
respectively.
There logically is no room for any other link or relationship between
summary and sub.
What else did you have in mind?
Greetings,
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional