How do I show float in a Microsoft Project schedule?

S

smallpuffydog

I am trying to show the foat time on a Microsft Project construction
schedule. I know how to show slack time, but I am looking for how to show
float. My definition of float is the time between when a task is scheduled to
end and when it has to be completed. In this case I am comparing the current
schedule to a baseline schedule.
 
J

Jan De Messemaeker

Hi,

Float is slack.
What you call float is called Finish Variance by Project.
HTH
 