S
Sean J. Miller
I have a 80,000 manhour MS Project 2007 file that takes 30+ minutes to level.
Is it possible to abort levelling once it begins processing without simply
ending the application with the Task Manager? I tried CTRL+Break and ESC,
but it continues to process.
Thanks,
Sean