How do I stop or abort leveling?

S

Sean J. Miller

I have a 80,000 manhour MS Project 2007 file that takes 30+ minutes to level.
Is it possible to abort levelling once it begins processing without simply
ending the application with the Task Manager? I tried CTRL+Break and ESC,
but it continues to process.

Thanks,
Sean
 
D

Dave

Sean said:
I have a 80,000 manhour MS Project 2007 file that takes 30+ minutes to level.
Is it possible to abort levelling once it begins processing without simply
ending the application with the Task Manager? I tried CTRL+Break and ESC,
but it continues to process.

Thanks,
Sean

I don't believe so. If this is a problem, then I suggest that you level
over specified date intervals. Having got satisfactory results, then
you can lock that interval by setting the priority to 1000 and level
over the subsequent interval.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top