I have found that if I assign resources to a task, schedule work, and enter
actuals, then go to the gantt chart view and update percent complete, the
actuals I have entered will be changed. this makes Project 2003 unuseable
for tracking progress against actuals, because actual work should never
change once its entered. How do I stop this behavior in Project 2003
Standard?