W
Wayne Bouwman
I'm looking to track Material Budget vs. Actual costs in a project.
When i create a task, "Buy Laptop Computer" for example and assign a
resource to the task with a resource type "material", and then I want to
enter a budget for it. I enter my budget value in the Cost field so that the
"budgeted" material cost will get rolled up with the "budgeted" resource
costs so that i can get an over Project Cost of "Material and Labor".
When I begin recording my actual hours and material cost, I can enter my
actual hours as a % Complete or actual hours in the % Complete or actual work
column. From that the Actual Cost column will be populated base on the
resource cost I've assigned to that task. An example is: Task 1 has resource
Joe assigned to it and Joe has an hourly rate of $25/hr setup for him in the
resource sheet. When I enter 2hr in the Actual Work column for Task 1, the
Actual cost column is recalculated to show $50.00. Great!
Now i want to enter my actual cost for the Computer Laptop that I had to
purchase. My Budget that i put in was $2,500.00 which i had put into the Cost
column when i setup the task. My actual cost was $2,300.00. When I try to
enter this value in the
Actual Cost column i cannot. Only after I enter a % Complete value in the %
Complete column can i enter my actual cost value. When i enter my actual Cost
value, it then updates the Cost (or my Budget) column to the $2,300.00. My
variance has just gone out the window and i cannot see what i initially
budgeted for my Laptop Computer.
How can I see my initial budget vs. my actual cost for this task?
I can probably do it by using Customer fields or something but I'd rather
not if at all possible.
Sorry for the long explanation.
When i create a task, "Buy Laptop Computer" for example and assign a
resource to the task with a resource type "material", and then I want to
enter a budget for it. I enter my budget value in the Cost field so that the
"budgeted" material cost will get rolled up with the "budgeted" resource
costs so that i can get an over Project Cost of "Material and Labor".
When I begin recording my actual hours and material cost, I can enter my
actual hours as a % Complete or actual hours in the % Complete or actual work
column. From that the Actual Cost column will be populated base on the
resource cost I've assigned to that task. An example is: Task 1 has resource
Joe assigned to it and Joe has an hourly rate of $25/hr setup for him in the
resource sheet. When I enter 2hr in the Actual Work column for Task 1, the
Actual cost column is recalculated to show $50.00. Great!
Now i want to enter my actual cost for the Computer Laptop that I had to
purchase. My Budget that i put in was $2,500.00 which i had put into the Cost
column when i setup the task. My actual cost was $2,300.00. When I try to
enter this value in the
Actual Cost column i cannot. Only after I enter a % Complete value in the %
Complete column can i enter my actual cost value. When i enter my actual Cost
value, it then updates the Cost (or my Budget) column to the $2,300.00. My
variance has just gone out the window and i cannot see what i initially
budgeted for my Laptop Computer.
How can I see my initial budget vs. my actual cost for this task?
I can probably do it by using Customer fields or something but I'd rather
not if at all possible.
Sorry for the long explanation.