G
GaffaUK
I have a project file which has work and duration fields entered in by days.
The work varies between 60 and 100% effeciency. E.g. Tom has a task which
should take 4 days and is entered into the work column as 4 days. However
under units this is 80% (effeciency) so the Duration comes out as 5 days.
So as a project Manager I want to be able to switch effortlessly between
viewing the Gantt chart in Duration (which it currently does) and Work (which
I can't seem to do).
Any suggestions greatly appreciated
The work varies between 60 and 100% effeciency. E.g. Tom has a task which
should take 4 days and is entered into the work column as 4 days. However
under units this is 80% (effeciency) so the Duration comes out as 5 days.
So as a project Manager I want to be able to switch effortlessly between
viewing the Gantt chart in Duration (which it currently does) and Work (which
I can't seem to do).
Any suggestions greatly appreciated