How do not show 100% completed projects in the list of Tasks in PWA
for employees

If a project is 100%, then I do not want to display it in the list of
tasks in PWA.

Because we complete many projects and people do not want to see
already completed projects

Thank you
 
J

Jonathan Sofer [MVP]

Try posting your question to "microsoft.public.project.server" instead. You
will have a better chance of getting your Project Server questions answered
there. Also, please specify the version of Project Server you are using as
the answers could be quite different.

BTW, to remove all project tasks from resources timesheets or task lists,
you can change all the booking types to "Proposed" and re-publish the
project. This works in PS2003 and PS2007 post SP1.
 