How do you assign a Lead Name

D

Dennis

I'm interested in assigning a Lead Name to resources in
Project Server 2003. I can't find any documentation or
help on this. I see the field in the time sheets, but
have not found a way to populate this field. Thanks in
advance for any help on this issue.
 
D

Dale Howard

Dennis --

The Lead Name field is populated when a team member delegates a task to
someone else. The person doing the delegating becomes the lead for the
delegated task. Hope this helps.
 