G
GHawkins
I'm working with a Project file using Project 2003. I have one resource who
requires a different Working Time calendar because of his location (working M
- S rather than M - F like everyone else on this project). I have that set up
for him within his Resource Information. However, whenever I assign him to a
task, the Finish Date doesn't update correctly. For example, one of his tasks
begins on 10/1/07 with a duration of 11 days. However, the Finish Date is
10/15/07 rather than 10/12/07 like I'd expect. The resource is 100% dedicated
to that task, and the task is a Fixed Duration with a constraint type of As
Soon As Possible. I'm not extremely familiar with Project - I'm working with
a file someone else created - and so I'm not exactly sure what else I need to
look at.
Any ideas? Any help is greatly appreciated!!
requires a different Working Time calendar because of his location (working M
- S rather than M - F like everyone else on this project). I have that set up
for him within his Resource Information. However, whenever I assign him to a
task, the Finish Date doesn't update correctly. For example, one of his tasks
begins on 10/1/07 with a duration of 11 days. However, the Finish Date is
10/15/07 rather than 10/12/07 like I'd expect. The resource is 100% dedicated
to that task, and the task is a Fixed Duration with a constraint type of As
Soon As Possible. I'm not extremely familiar with Project - I'm working with
a file someone else created - and so I'm not exactly sure what else I need to
look at.
Any ideas? Any help is greatly appreciated!!