E
Ed
1) I am working with VP of IT who has used project in the past and wants
to see the project dates slide automatically (no manual finish date change).
Currently these tasks types are defined as fixed units. Will changing them
to duration based tasks enable this funcitonality?
2) Also, is there a method of changing the task font color to red in
the Gantt Chart when this happens?
I personally don't remember that functionality existing in the product
but I have always used fixed units as the task type.
3) Last question: Showing slack on the Gantt Chart results in a very
hard to read small line, and forcing task critical if the remaining days are
less than xx days will work to force the tasks critical.
Do you have a configuration recommendation on how to show critical
path slipping, or slack being depleted without setting changing that critical
task day(s) slack variable to a ?? number of days.
to see the project dates slide automatically (no manual finish date change).
Currently these tasks types are defined as fixed units. Will changing them
to duration based tasks enable this funcitonality?
2) Also, is there a method of changing the task font color to red in
the Gantt Chart when this happens?
I personally don't remember that functionality existing in the product
but I have always used fixed units as the task type.
3) Last question: Showing slack on the Gantt Chart results in a very
hard to read small line, and forcing task critical if the remaining days are
less than xx days will work to force the tasks critical.
Do you have a configuration recommendation on how to show critical
path slipping, or slack being depleted without setting changing that critical
task day(s) slack variable to a ?? number of days.