I am having some difficulties blocking vacation time for each resource
in Project Server 2007. Can anyone tell me the exact steps to do
this?
Thanks,
Mickey
Mickey,
Jonathan's method certainly works, but if you are using Timesheets and
Administrative time, simply have the resources enter vacation time in
the future. Try this experiment to replicate my results:
1. Open a future Timesheet - I chose a week in March
2. Enter 8 hours a day x 3 days for that week in the Vacation row
3. Submit using your process
4. Open Project and set the start date to March 1, 2008
5. Assign yourself to a task and enter a task duration sufficient to
cover the vacation days. In my case, I entered 15 days.
6. Note that while the duration is 15 days, the Gantt bar and the
Start and Finish dates reflect 18 days of effort (15 work days + 3
days vacation).
7. You can also see on the Resource Calendar that the time is blocked
and the Exception name is My Timesheet
Hope This Helps,
Mark Everett, PMP
www.catapultsystems.com