How do you change a WBS number from 1 to 2 etc.

L

Lee

Good Morning!

How do you change a WBS number and its' sub numbers?

What I have is:
1
1.1
1.1.1
1.1.2

What I want is:
2
2.1
2.1.1
2.1.2

Thanks.

Lee
 
M

Mike Glen

Hi Lee,

Welcome to this Microsoft Project newsgroup :)

The simplest way is to Insert a task above your first one - say create a project start milestone. This will then become number 1 and your next task (summary) will become 2, etc

FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials



Good Morning!

How do you change a WBS number and its' sub numbers?

What I have is:
1
1.1
1.1.1
1.1.2

What I want is:
2
2.1
2.1.1
2.1.2

Thanks.

Lee
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top