How do you get the Resource Sheet to work on rolled up project plans?
I usually work on 10-15 seperate project plans at the same time.
All of these individual .MPP files use the exact same Resource Sheet of 20
resources. Same titles, same order.
So when I insert, say 10 of these project plans into one master .MPP rollup
the Resources of each individual .MPP get copied and added to a long list. A
list that is 200 resources long instead of the 20 it is supposed to be.
Help if you can.