You could use Deadline Dates which will tell you if you passed the desired
date.
Since these are "target dates" it sounds to me that you are using them as a
baseline.
You can save a baseline by going to Tools/Tracking/Save Baseline... This
will store all the dates, durations, work, cost, etc. into special baselne
fields: Baseline Start, Baseline Finish, Baseline Duration, etc. The
baseline dates will not change unless you overwrite the baseline. So, you
can compare "start" to "baseline start" simply by inserting both columns.
Also, run the Gantt Chart Wizard (Format/Gantt Chart Wizard...). Select the
option to show the baseline. Now your Gantt Chart will show two sets of bars
for each baselined task --- one is "forecast" and the other is the baseline
your "memorilalized" when you set the baseline. Now you graphically can see
the slips in your schedule.
HTH
--
If this post was helpful, please consider rating it.
Jim Aksel, MVP
Check out my blog for more information:
http://www.msprojectblog.com