R
Ron
I am creating a custom field that would compare the actual
%complete to the Planned % complete based on duration. So
on a task that has a 10 day duration if we are 5 days into
it and the %work complete is less than 50% the field will
use a graphical indicator to flag it as slipping. But I
first need to set up a field that returns a percent value
and I have had no luck doing this yet....Any help would be
greatly appreciated
Thanks,
Ron
%complete to the Planned % complete based on duration. So
on a task that has a 10 day duration if we are 5 days into
it and the %work complete is less than 50% the field will
use a graphical indicator to flag it as slipping. But I
first need to set up a field that returns a percent value
and I have had no luck doing this yet....Any help would be
greatly appreciated
Thanks,
Ron