M
Munem
My organization's contractor policies do not enable us to load true rates
into Project Server. Due to this, I have some challenges extracting BCWS. The
Enterprise Resource Pool uses bogus rates (which I cannot change due to more
red tape). Consequently, I would like to only extract the BCWS in hours by
resource, and then apply the real rates on my own in Excel.
Unfortunately I can't seem to isolate BCWS in hours. In addition, because of
the presence of a $0 Overtime Rate (another enterprise restriction), I can't
even back into the BCWS hours by pulling the BCWS and Standard Rate fields.
Any suggestions would be much appreciated!
into Project Server. Due to this, I have some challenges extracting BCWS. The
Enterprise Resource Pool uses bogus rates (which I cannot change due to more
red tape). Consequently, I would like to only extract the BCWS in hours by
resource, and then apply the real rates on my own in Excel.
Unfortunately I can't seem to isolate BCWS in hours. In addition, because of
the presence of a $0 Overtime Rate (another enterprise restriction), I can't
even back into the BCWS hours by pulling the BCWS and Standard Rate fields.
Any suggestions would be much appreciated!